Floor switch and blade center migration

For the past two weeks me and another engineer have been coming in an hour earlier everyday to move our access layer switches to the Nexus 5548s. It was quite the tedious process but at the same time it was a great experience. This move involved migrating the access switches to 10Gb as well as utilizing Etherchannels up to the 5548s. The 5548s also had to be configured with etherchannels/vPCs down to the access layer. We did 1-2 IDF closets a day so the process did take quite some time. However this morning we finished it all up :)

This past weekend we had a maintenance window from 1am to 7am. During this time frame we had to migrate 7 blade centers to the Nexus 7010. There were also a few other tasks that we needed to do such as moving over some management cables and a few “not so important” servers. Again etherchannels and vPCs needed to be used between the Nexus and Bladecenters. All in all it was a pretty smooth transition. The last thing we need to do now is remove some left over items that are still hanging off the 6509s. After that the Nexus migration project will come to an end :(

 

Leave a Reply

Your email address will not be published.

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>

Current month ye@r day *

Notify via Email Only if someone replies to My Comment

networking-link.com is a participant in the Amazon Services LLC Associates Program, an affiliate advertising program designed to provide a means for sites to earn advertising fees by advertising and linking to Amazon.com.